News

Published June 8, 2023

Prep work for Highway 400/Dunlop Street bridge replacement to begin, and for motorists, travel headaches

Sanitary sewer construction project to begin in a few weeks

News Release - City of Barrie

The infrastructure located around the Edgehill/Cedar Pointe Drive/Dunlop Street/Hart Drive area needs to be relocated to prepare for the upcoming Ontario Ministry of Transportation (MTO)’s interchange and bridge replacement project at Highway 400 and Dunlop Street.

This sanitary sewer construction project will be starting in the next few weeks, and will take approximately a year to complete. 

The work will start on Hart Drive before crossing the highway to Dunlop Street, then work will progress to the Dunlop/Cedar Pointe Drive intersection, and will move along to Edgehill Drive. Detours will be in place and Barrie Transit routes 5 and 6 will be detoured during the work.

During construction (between 7 a.m. and 7 p.m., Monday to Friday), access to Hart Drive, Dunlop Street, Edgehill Drive, and Cedar Pointe Drive will be restricted. There will also be some night and weekend construction work. Emergency services will have access at all times and local businesses will remain open.

The work will include the following:

  • Cedar Pointe Drive will be closed for approximately three months. Businesses along Cedar Pointe Drive will remain open for business throughout the duration of construction, but Cedar Pointe Drive will be closed and access to businesses will only be from Edgehill Drive.
  • Lane restrictions will take place on Hart Drive. All businesses along Hart Drive will remain open throughout construction.
  • The Cedar Pointe Drive/Edgehill Drive intersection will be fully closed for approximately three months.

Residents are reminded to follow detours, use caution, plan ahead, and expect delays if travelling through this area.

This construction project is a key part to prepare for the MTO’s work for the Dunlop Street bridge replacement. At the completion of this project (summer 2024), the MTO will start the Dunlop bridge replacement project, which is expected to take approximately four years to complete.

For updates on the Dunlop Street Sanitary Relocation project, visit barrie.ca/roadwork.

Banner image provided by City of Barrie

What do you think of this article?
+1
0
+1
0
+1
0
+1
0
+1
0
Advertisement
Advertisement
Advertisement

Have a breaking story?

Share it with us!
Share Your Story

What Barrie's talking about!

From breaking news to the best slice of pizza in town! Get everything Barrie’s talking about delivered right to your inbox every day. Don’t worry, we won’t spam you. We promise :)
Subscription Form
Consent Info

By submitting this form, you are consenting to receive marketing emails from: Central Ontario Broadcasting, 431 Huronia Rd, Barrie, Ontario, CA, https://www.cobroadcasting.com. You can revoke your consent to receive emails at any time by using the SafeUnsubscribe® link, found at the bottom of every email. Emails are serviced by Constant Contact

Related Stories

Advertisement
Advertisement